The project is still going
ahead but the jobs that need to be done now have waiting times in between and
we’re also working with other sub-contractors who are busy at this time of
year. These are the major happenings on
the project work days:
Day 13 Concrete floor poured inside
Day 14 Prep for the outside concrete pour
Day 15 Concrete pour outside and back step
Day 16 Electrical work started, windows and doors
installed
Day 17 Outside trim around doors and windows. I had to fill nail holes and paint a second
coat after they were up.
Day 18 More electrical work, conduit for wire to
breaker box in basement
Day 19 Insulation—very pink
Day 20 Vinyl siding first day
Day 21 Vinyl siding second day—all done!
While all this work was
going on, we also kept ourselves busy with our own projects and took some time
off to play golf and make a trip to Colville ,
WA . I’ll share our projects with you after the
garage is finished, hopefully in another week or so.
looks done to me, amazing how many steps are required to finish a garage. I'm impressed by how seamlessly is blends with the house.