A project
that we have been planning to do for quite a while now has been to do some
landscaping along the length of our driveway.
It has always been an untidy and uneven area of mixed grass and weeds
that was dry and dusty in the summer, a challenge for mowing and weed
whacking.
Back in August, we contacted a
contractor to remove the sod, level the ground and spread bark mulch on the
whole area. He was willing to do the
work almost any time but first, we needed to get a huge (45 cubic yards)
delivery of bark mulch. We were able to
order it from Kalesnikoff Lumber north of Castlegar, but we had to wait until
they were cutting fir at the mill as that is what makes the best bark
mulch. That didn’t happen until
September, so the bark mulch was delivered and dumped in our driveway on September
23.
We
went ahead and spread some of it at the top of the driveway opposite the house to
see what it would look like. Nice, but a
lot of work with a wheel barrow.
Our
contractor was able to work on the project in the middle of last week and spent
2 half days doing the job. He removed
the sod, hauled it away and back bladed along the sides to level and pack them
down. He had 2 helpers with shovels and
rakes who worked on the edges.
Then
it was time to dump and spread the bark mulch.
That went quickly with the 2 guy plus Stuart raking out the piles that
were dumped by the machine. We put 4
inches of mulch over the area as that is supposed to be the right depth to
block weeds from growing up. Hopefully,
that works—we don’t want to see weeds or grass in the mulch.
After
the sides of the driveway were finished, we pressure washed the whole thing to
clean off all the debris in preparation for seal coating. We had to connect every hose we owned to
reach the end of the driveway (300 feet) and even then, the last few feet were
just at the edge of the spray. It
cleaned up well, though.
The
next day, the two of us started rolling on the asphalt sealer and that was a
big job. We started at the house and
shop and worked our way down the driveway.
We spent about 7.5 hours at it and were exhausted by the end of the
day. It was important to get it all completed
as the weather was good (cloudy but dry) and you can’t drive on it until the
next day.
We
did some touch ups the next morning and then took a well-deserved rest. We used eleven 5 gallon buckets for the job
which was about 8,000 square feet.
So
now we’re all done with our home projects for the year and can do a little more
recreating before getting ready to winterize everything. We went out in the boat on Christina Lake a
week ago and have been grouse hunting a few times. Stuart got 3 grouse one day and 1 another
day. He used a shotgun the first time
and then used the .22 rifle after that.
We plan to go out turkey hunting later this week. The weather is still warm and sunny—an
amazing autumn so far.
No comments:
Post a Comment